For a company and a period: each check that blocks a close, with its findings and their value, in the order they are cleared. These are the controls Sage’s pre-closing verification report CLOPER makes when someone runs it, made every night instead. Close readiness is a view: it stops nothing in X3.

Prerequisites. You hold every site of the company (see Who sees what). For a company you do not, it shows no line, Status empty, and Run close checks says only how the run ended.

Block Company and period

Field What to enter or what it shows
Company The company. From the board’s company line, that company.
Date in the period A date of the period to check: the board line’s period when opened from it, else the company’s next period to close.
Period start, Period end The period the date gives.
Status Ready: no finding blocks its close. Not ready: findings block it. Not checked: a blocking check did not finish.

A date gives the company’s period that holds it and ends first, the lowest ledger type’s on a tie; X3 says so when no period holds it. Status is in its colour, as on the board, and Not checked holds until that check finishes when it next runs.

Block Blocking checks

One line per check that blocks a close, in close order. A blocking check of step 0 comes after the others, by its code.

Field What it shows
Close step The check’s place in the order, set in Check setup.
Check, Description The check, and its name.
Blocking findings Its findings New, Open or Worse in the company and the period. An acknowledged finding blocks nothing until its end.
At stake, Currency Their value.

A finding is in the period when its document is dated within it, as CLOPER takes it; check 6’s when its period is left open behind this one; a finding with no date is in every period.

A line’s Actions hold Findings, which opens the check’s findings in the company.

Buttons

Button What it does
Run close checks Runs the checks that block a close now, then reads the list again. X3 then says how many findings block the close, why a check that blocks it did not finish, or that the period is ready to close. When the run itself did not finish, X3 says why instead.
Refresh list Reads the list again.

Beside Sage’s CLOPER

Close readiness differs from CLOPER in three points:

  • Entries waiting on the accounting task. CLOPER lists them by journal type and blocks the close on them. No check finds them: run CLOPER before the close for them.
  • An entry whose lines do not balance (check 5) blocks here. CLOPER names such an entry only as temporary, and a period closed on it leaves a wrong ledger.
  • A stock count left open (check 17) blocks here, which CLOPER does not check: stock counted after the period’s end values the period’s stock wrongly.

Passing a block

A block is yours to pass:

  • For one finding: acknowledge it with a reason and an end date. It blocks nothing until that date.
  • For a check: in Check setup, untick Blocks the close, or change its Close step. The values that ship are defaults.

Stuck? Ask your Sage partner, or write to info@nortiqo.com.

Email us