A price list GESSPL

Contents

The policy that governs price lists acts in Sage’s own function for them. It governs a price list’s validity and its lines: which product or customer pays what price, from what quantity. Users work there as before; only a save that changes a governed value asks for a signature.

Prerequisites. E-signature’s entry point on price lists, object SPL, from the install guide, and an active policy of object SPL whose lines on tab Condition choose the price lists it governs. The ready-made policy PRICES governs every price list; narrow it by its lines, to a price list code. A new price list is judged by the price list code it is created under.

The fields. E-signature signs a change to the price list’s validity PLISTRDAT and PLIENDDAT, and to the ten fields of each line that Sage’s import carries: its first two criteria, unit, minimum and maximum quantity, currency, price and its first three charges or discounts; and a line added or deleted, a line known by its number. Every line takes the price list’s validity with it. A save that changes a line’s criteria 3 to 5 or its charges 4 to 9, or gives them to a line added, is refused: E-signature cannot sign them. The lines’ other fields, their amounts, price factor, lead time, free goods and commission, save as before, and a line added by a signed change takes Sage’s defaults for them.

A change. Change the price list and save.

  1. The signing dialog opens, meaning Authored: each changed value with its old and new value, a line’s by its number; a line added with its ten values, a line deleted with its criteria and price.
  2. Sign. One box, titled Nortiqo E-signature, says that the change needs approval and gives its change set’s number, and its last line says that any other changes the save held were not stored either. Nothing is saved until the change is approved and applied.
  3. Close the dialog instead: nothing is submitted.

A changed validity shows once, on the price list, and every line takes it. A save that changes no governed value, or a price list outside the policy’s condition, saves as before, with no dialog. A save that adds more than twenty lines, or twenty with any other change, holds more values than one change carries, and is refused: put a larger addition into a new price list, created ended, and put it in force by a signed change of its validity.

A new price list is created ended, its end of validity before today, with no dialog; a governed price list created in force, in the window or by an import, is refused. Putting it in force is then a signed change of its validity, which every line takes. A document dated within an ended price list’s validity still takes its prices.

A deletion of a governed price list is signed by its author as it is deleted, as a product-site’s is.

  1. Delete the price list. Before anything is deleted, the signing dialog opens, meaning Authored, its values titled Deletion – the record as stored: the price list’s validity, and each line’s ten values by its number, every line stored and not only those the window shows. A price list of twenty lines or more holds more values than the dialog shows, and is signed by its validity and the number of its lines instead.
  2. Sign. The price list and its lines are deleted and the signature is written in the same transaction; Sage’s own message that the price list is deleted follows, and no box of ours. Nothing waits for an approver: the policy’s later steps do not apply to a deletion.
  3. Close the dialog instead: nothing is deleted.

A price list changed between the signature and the deletion stops the deletion: delete again. A signature that cannot be written stops it too. An import, a web service or a batch deletes no governed price list.

When a save is refused, nothing is saved, for the reasons a supplier’s is (A supplier’s bank details). A save is also refused for a price list with more lines than the window loads, or with a line numbered 0 or with another line’s number. An import of template SPL that changes a governed price list is refused or submitted as the policy’s channels say.

When an approved change is not applied. A change is submitted and signed, but not applied, the change set ending Apply failed, when Sage’s import would store anything other than the signed change. It goes back to its author when the price list changed after it was submitted: a line it adds whose number another line has taken since, or a line it deletes whose criteria or price changed.

Not seen by the policy: Sage’s sales price revision writes price lines without a signature, and so does a change of a price list code’s setup whose question to delete the code’s lines is answered yes, which deletes every price list of the code. The revision also creates price lists in force. The integrity monitor reports what they change of a governed price list, and one created in force as a change of its end of validity.

Stuck? Ask your Sage partner, or write to info@nortiqo.com.